Eskom gets Kusile Unit 5 boost to end load shedding

Kusile Unit 5 not only boosts baseload capacity but also enhances grid stability, with the additional inertia of the generator making it easier to onboard renewables after installing the required transmission lines.
"The delivery of this unit is a testament to the collective effort of our 40,000 employees," said Bheki Nxumalo, Eskom executive for generation, who extended gratitude to all involved in bringing Unit 5 online.
This achievement aligns with Eskom's winter outlook, published in April 2024, which outlined plans to add 2,500MW to the grid by the end of the year.
Eskom CEO, Dan Marokane, reiterated the company's commitment to operational recovery, governance improvements, and futureproofing the organisation to ensure energy security for South Africa and the broader region.
“Eskom will continue to focus on implementing operational recovery, strengthening governance and future proofing the organisation to enable energy security, growth and long-term sustainability to the benefit of South Africa and sub-Saharan Africa,” he said.
Unit 5 shines
Unit 5 has consistently met performance targets during the testing period and has played a role intermittently supplying electricity in the power utility’s load shedding reduction efforts.
Once completed, Kusile Power Station, with six units, will boast a maximum output of 4,800MW. Notably, Kusile is the first power station in Africa equipped with wet flue gas desulphurisation (WFGD) technology, reducing sulphur dioxide emissions and adhering to international air quality standards.
Kusile, South Africa's largest construction project, is set to become the world's fourth-largest coal plant upon its eventual completion.
Construction of the final unit, Unit 6, is however progressing as planned, with synchronisation to the grid expected in November 2024 before full operation in 2025.
Incoming shutdown of 3 units
While this is a significant stride in the country's fight against load shedding, Eskom continues to have the emissions compliance sword dangling over its head.
The power utility has been operating Kusile units 1, 2, and 3 under a postponement of minimum emission standards due to ongoing repairs on permanent flue gas ducts.
Eskom assures the public that emissions remain within permissible limits and that measures are in place to mitigate any potential impact on air quality and public health.
There is, however, no comment on the contingency plan or timeline for removing the three units from service when the permanent fix is installed.
For now the news off additional generating capacity coming online is welcome as winter settles in across the country.

Related
#Budget2025: Implications for renewable energy solutions private producers 2 days #Budget2025: Unlocking mining's full potential could reshape South Africa's economy 13 Mar 2025 Load shedding rollercoaster is not sabotage related 24 Feb 2025 Mantashe adds Russia and Iran to nuclear chat 19 Feb 2025 Eskom posted profit, then brought back load shedding 31 Jan 2025 Eskom tariffs to rise by 12.7% 30 Jan 2025