BREAKING l Stage 2 load shedding from noon today till 11pm Sunday
“The load shedding is necessary due to loss of generation capacity overnight. It is also required to manage the use of the emergency reserves, which will help us contain the stage of load-shedding required," the power utility said in a statement.
Two generation units at the Kusile power station tripped as a result of the main coal feed conveyor belts supplying coal to the units failing. In addition, a unit each at the Kriel and Duvha power stations tripped due to unforeseen breakdowns. Four generation units' return to service from planned maintenance has also been delayed.
“The system remains vulnerable and unpredictable, should any further breakdowns occur, the stage of load shedding may change at short notice," Eskom said.
Eskom currently has 5,358MW on planned maintenance, while another 14,748MW of capacity is unavailable due to unplanned maintenance, breakdowns and the outage delays.
Related
DPWI in hot water again over Mbombela High Court crisis Lindsey Schutters 4 Nov 2024 Justice committee blasts DPWI over court infrastructure crisis Lindsey Schutters 25 Oct 2024 There may just be no load shedding this summer Tannur Anders 27 Aug 2024 Lesotho Highlands Tunnel closure will not affect water availability 26 Apr 2024 Second Johannesburg gas blast - five admitted to hospital after Braamfontein maintenance accident Michelle Banda 6 Sep 2023