Nersa rejects Eskom's plan, wants sustainable prices

Eskom is mired in a financial crisis and is struggling to power the country's economy because of regular faults at ageing coal-fired plants that provide most of the country's electricity.
The revenue applications, if approved by the regulator, provide an important mechanism for Eskom to claw back money from customers via tariffs.
In January, Nersa allowed Eskom to recoup an additional R6bn after a court set aside several of its earlier decisions.
"The energy regulator will request Eskom to submit a one-year interim application for the 2022/23 financial year, preferably based on the principles of a new approach that is under consideration," it said in a statement.
It had rejected Eskom’s fifth multi-year price determination (MYPD5) revenue application for the financial years 2022/23, 2023/24 and 2024/25 on the basis that it was based on an expired methodology.
Source: Reuters

Reuters, the news and media division of Thomson Reuters, is the world's largest multimedia news provider, reaching billions of people worldwide every day.
Go to: https://www.reuters.com/Related
Load shedding rollercoaster is not sabotage related 24 Feb 2025 Mantashe adds Russia and Iran to nuclear chat 19 Feb 2025 Eskom tariffs to rise by 12.7% 30 Jan 2025 Mozambique's Maputo port kicks off $2bn upgrade 29 Jan 2025 Mining operational costs stabilise as 2024 closes, but challenges persist 17 Dec 2024 Ramokgopa withdraws nuclear determination, undoing more Mantashe policy 9 Sep 2024